Various Services
Abbotshaugh Gas Peaking Plant
ClientG2 EnergyValue£560,000LocationFalkirk
Description of works
Civils works at the new Abbotshaugh Gas Peaking Plant
In early 2022 Ready Construction were awarded the contract for the civils works at the new Abbotshaugh Gas Peaking plant in Falkirk from G2 Energy. the works included in this contract were the breakout of the existing concrete surface and reduced dig of the site, the installation of palisade fencing around the site perimeter, the installation of the new concrete foundations for the storage and transformer units to be landed upon, the ducting and cable routes connecting the units, the services trench for the new gas feed into site, the road and footpath construction and finally the dress off and finishing works to site.
The works faced challenges straight away as the new site lay directly beneath the 132,000V wires from the substation pylon located in the land directly beside the site so careful planning and preparation had to go into all works to ensure that machines were fitted with restrictors and unable to work within a certain distance of the wires, laydown areas had to be placed in areas that wouldn’t cause issues with loading and unloading and similarly with concrete pump / crane pad setup to allow for the concrete bases to be poured and the units lifted into position once the bases had cured. These works were all coordinated with the help of the local SPEN Engineer, the HSE GS6 document & the Energy Network Association’s Technical Document 43/8 to allow for exclusion zones to be set up in the correct locations and for RAMS to be created to ensure everyone on site was briefed and understood the safe methods of working along with the risks involved.
The site was stripped and cleared before the concrete bases were installed. The bases were an integral part of the site as they had to be poured in not only precise locations to ensure the minimum distances between the storage units was achieved in what was already a tightly packed site but also to ensure that the top hat sections of the founds were all poured to an accurate height allowing the units to be landed onto them to sit level with the required depth for cabling and services underneath. To ensure this the site engineer checked all shuttering and formwork as well as steel cage and starter bar locations before any pouring took place.
Once the concrete bases were in place and allowed to cure the cable & service routes were pulled through the site. As the storage units were fed by gas a new gas feed had to be brought to site from the existing main on the road outside the site. To allow for this to happen road closures and traffic management had to be setup to allow for the works to be carried out safely and to maintain access to the local businesses while minimising disruption to the general public. The local council representatives as well as the local business owners were consulted and agreements put in place before the works commenced to ensure all parties were happy with the arrangements. The service trench was then dug as per the agreements with the SGN install team and then backfilled accordingly once the new main was installed, tested and signed off.
Once the storage units were landed in place the finishing works were carried out around the site dressing off and creating the road in for future works and maintenance and installing the palisade fence with both pedestrian and vehicle gates around the site perimeter before handing the site back to the client.
All works were carried out without accident and incident in what was at times a tricky but mostly straight forward project for the team involved.
Approach
The works comprised the following principle elements:
Approach
Safety-first planning under 132 kV overhead lines – plant fitted with height restrictors; crane / pump pads and lay-down areas set outside GS6 & ENA 43-8 exclusion zones in consultation with SPEN.
Detailed RAMS and briefings – all operatives inducted on hazards, safe working distances and lift plans before tasks began.
Stakeholder coordination – early engagement with Falkirk Council, neighbouring businesses and SGN to agree traffic-management, road-closure windows and service-trench methodology.
Engineering accuracy – site engineer verified all formwork, re-bar cages and levels so “top-hat” concrete bases met tight positional and height tolerances.
Zero-incident culture – continuous supervision, daily toolbox talks and proactive issue resolution delivered the project without accidents or reportable incidents.
Scope of Work
-
Break-out and removal of existing concrete surface, followed by reduced-level dig and full site clearance.
-
Installation of palisade perimeter fencing with pedestrian and vehicle gates.
-
Construction of reinforced-concrete foundations for storage and transformer units.
-
Provision of temporary crane and concrete-pump pads for lifting and pouring operations.
-
Installation of underground ducting and cable routes between all plant items.
-
Excavation and backfilling of a new services trench; connection of a new gas main from the public road.
-
Construction of on-site access road and footpaths for future maintenance.
-
Final dress-off, compaction and general finishing works prior to client hand-over.